RTA Status Reports – Sept. 2020

RTA Project Status – Through Aug. 31
Projects in design 39
Under Construction/Implementation 53
Total Number Completed 870
RTA Financial Status – Through Aug. 31
Collections $1,040M
Funds Expended $1,319M
Fund Balance $113.9M

870 RTA projects completed, including:

  • 186 intersections of 200 promised
  • 75 pedestrian crossings of 80 promised
  • 136 bus pullouts of 200 promised
  • 170 miles of new sidewalk of 250 miles promised
  • 338 miles of new bike lanes of 550 promised
  • 16 roadway corridors completed
  • 10 roadway corridors partially completed