RTA Project Status – Through August 2025 |
|
|---|---|
| Projects in design | 84 |
| Under construction/implementation | 74 |
| Total number completed | 1,048 |
| RTA Financial Status – Through March | |
| Funds expended to date | $1.73 B |
Over 1,000 RTA projects completed, including:
- 202 of 200 intersections promised (two additional intersections added)
- 84 of 80 pedestrian crossings promised (two additional crossings added)
- 180 of 200 bus pullouts promised
- 183 of 250 miles of new sidewalks promised
- 370 of 550 miles of new bike lanes promised
- 18 roadway corridor completions
- Also, 11 roadway corridors partially completed