| RTA Project Status – Through May 31 | |
|---|---|
| Projects in design | 55 |
| Under construction/implementation | 46 |
| Total number completed | 895 |
| RTA Financial Status – Through May 31 | |
|---|---|
| Collections | $1.1B |
| Funds expended | $1.3B |
| Fund balance | $156M |
895 RTA projects completed, including:
- 194 of 200 intersections promised
- 76 of 80 pedestrian crossings promised
- 139 of 200 bus pullouts promised
- 179 of 250 miles of new sidewalks promised
- 366 of 550 miles of new bike lanes promised
- 17 roadway corridor completions
- 9 roadway corridors partially completed